煤炭工程 ›› 2025, Vol. 57 ›› Issue (4): 34-40.doi: 10. 11799/ ce202504006

• 施工技术 • 上一篇    下一篇

高冲击韧性锚杆(索)主动支护技术

杨超,付玉凯,董亚东,等   

  1. 1. 开采研究院
    2. 天地科技股份有限公司
  • 收稿日期:2024-04-16 修回日期:2024-08-26 出版日期:2025-04-10 发布日期:2025-05-28
  • 通讯作者: 付玉凯 E-mail:543913570@qq.com

Active support technology of high-impact toughness bolts (cables)

  • Received:2024-04-16 Revised:2024-08-26 Online:2025-04-10 Published:2025-05-28

摘要:

针对冲击地压巷道围岩变形破坏严重、支护强度低等难题,分析了应力波对巷道的影响,开发了高冲击韧性锚杆(索),提出了高冲击韧性锚杆和高强锚索协同防冲作用机理。以母杜柴登矿30207风巷为工程背景,依据巷道条件环境,从支护材料和支护体结构进行了高冲击韧性锚杆(索)支护的设计与应用。从现场监测结果可知,试验区巷道变形得到明显控制,变形主要以底鼓和两帮变形为主,巷道掘进期间底鼓量达到400mm,两帮移近量达到300 mm。随着巷道掘进,顶板锚杆(索)受力逐渐稳定,受力分别为170kN、150kN;回采帮锚杆(索)受力差别较大,锚杆轴力逐渐损失并逐步稳定;煤柱侧帮锚杆受力波动大,锚索受力相对较小,受力位于70~110kN。总体来看,该支护方案提高了巷道支护强度,保证了巷道围岩稳定性,支护效果良好。

关键词:

冲击地压 , 高冲击韧性锚杆(索), 主动支护 , 巷道围岩控制

Abstract: In order to solve the problems of serious deformation and damage of the surrounding rock and low support strength of the impact ground pressure roadway, the influence of stress wave on the roadway was analyzed, the high-impact toughness bolt (cable) was developed, and the synergistic anti-scouring mechanism of the high-impact toughness bolt and the high-strength anchor cable was proposed. Based on the engineering background of the 30207 wind tunnel of Mudu Chaideng Mine, the design and application of high-impact toughness anchor (cable) support were carried out from the supporting materials and supporting body structure according to the roadway conditions and environment. From the on-site monitoring results, it can be seen that the deformation of the roadway in the test area has been significantly controlled, and the deformation is mainly based on the deformation of the bottom drum and the two gangs, and the bottom drum volume reaches more than 400mm during the roadway excavation, and the distance of the two gangs reaches 300mm. With the roadway excavation, the force of the roof bolt cable is gradually stabilized, and the force is 170kN and 150kN respectively. The force of the mining help bolt (cable) is quite different, and the axial force of the bolt is gradually lost and gradually stabilized; The force fluctuation of the side bolt of the coal pillar is large, and the force of the anchor cable is relatively small, and the force is located at 70-110 kN. On the whole, the roadway support strength is improved, the stability of the roadway surrounding rock is ensured, and the demonstration effect is good.

中图分类号: